The Urban Housing Policy
Debate
Housing Programmes
H ousing for
All is a priority commitment for the Indian Government. The vision is
that every family will have a pucca (permanent) house with water
connection, toilet facilities, 24Χ7 electricity supply and access. The
programme proposes to build 20 million affordable houses for the
economically weaker section in metros, small towns and all urban areas
of India by 2022. The budget has allocated Rs 22,407 crore for the
housing and urban development sector for this fiscal year.
Housing schemes have been planned and implemented
before, without reaching the goal of eliminating homelessness. The
Jawaharlal Nehru National Urban Renewal Mission (JNNURM), launched in
2005, was the first and biggest effort in the post-independence history
of India to comprehensively address urban development. The scheme ran
from 2005 to 2014, after being extended by two years for the completion
of delayed projects.
In 2012, the Ministry of Housing and Urban Poverty
Alleviation (HUPA) pegged the housing shortage at 18.78 million units,
with 96% of this demand in the affordable housing space. With the gap
expected to grow to 38 million units by 2030 (MGI, 2010), the new target
still falls short of eliminating homelessness. Thus it is important to
understand the causes behind this implementation gap.
Implementation Gaps
While policies do exist, there have been multiple
gaps in the
translation of these policies into implementation that reduce the
impact. A progress study by HUPA in September 2013, showed that only 47%
of the dwelling units sanctioned under JNNURM had been completed. In
Punjab, 87% of the units sanctioned were either not started (48%) or not
completed (39%). The discrepancy between disbursement of Central
Assistance (ACA) and completion of dwelling units on the other is
particularly striking in some states and highlights implementation
difficulties. In Sikkim, 94% of ACA had been released, but only 17.7%
sanctioned dwelling units had been built. In Rajasthan, 73.3% ACA had
been disbursed, but only 19.3% of units had been completed. A year
later, only about 59% of the dwelling units sanctioned across the
country had been completed but 87.6% of committed funds were released.
Additionally only 43% units were actually occupied. 
Thus the scheme was unable to meet its target of
providing shelter both due to units not being constructed as well as
lack of occupation in the completed units. Low retention and acceptance
of social housing projects is not just limited to JNNURM. Similar
experiences have been seen in many other state and centrally sponsored
housing schemes. A study to gain insights and a deeper understanding of
the situation on the ground reflected some causes of these lack lustre
statistics. They are illustrated below.
Land
Constraints
The responsibility for provision of land - a prime
resource for housing lies with the government. Consultations with key
stakeholders across various states in India revealed that a major
bottleneck for affordable housing projects is adequate availability of
land. Most medium to large cities do not have enough land near the city
centre, thus slums and new housing projects (especially affordable) are
relocated on the outskirts of the city, often beyond the municipal
boundaries. This relocation adversely affects the displaced populace by
removing them from their livelihood, often distancing them from basic
amenities like markets, hospitals and schools. Travel routes are also
not well developed especially in the smaller towns to ease the
transition. This relocation is often quoted as the single most important
reason for attrition and desertion of these allotted houses.
Financial
Mismanagement
The HUPA JNNURM progress study found instances of
fund diversion from housing projects towards other initiatives such as
toilet construction (Jammu & Kashmir), DPR preparation (Jharkhand),
agency charges (Haryana) etc. This has obvious adverse effects on
progress.
Another area of concern is the cost escalation due to
inflation between the project planning and construction stages. The
centres share is fixed. The urban local body or implementation agency
often cannot bear this expense and they end up passing it on to the
consumer. Further delayed release of funds as is often the case in
government projects, exacerbates the situation. Projects often get
stalled due to this reason. This was observed in self-financing schemes
such as the Rajiv Swah Gruh Scheme in Andhra Pradesh where the
implementation agency was unable to bear the costs and the scheme shut
down.
Quality of
Construction
Construction of housing especially in the numbers
required to meet the demand is very resource intensive. Resource
efficiency in materials and technologies can go a long way in reducing
this pressure on resources and the environment as well in reducing the
cost of construction. However, they are often not mainstreamed in
construction and the government schedule of rates that govern material
use. Additionally, limited technical capacities of implementation
agencies on these alternative materials and technologies retards the use
of these options.
While this is true for all housing and construction,
the affordable housing sector faces a serious acceptance issue from
users due to the common perception of these alternates. The Kerala
experience shows that use of these technologies in institutional and
high income construction creates a demonstration effect increasing
acceptance within the LIG (Low Income Group) and EWS (Economically
Weaker Section) sectors.
Another concern among home owners is the small size
of houses allocated. EWS houses are in the range of 21-27 sqm carpet
area. This barely accommodates a bedroom, a common room and a tiny
kitchen. The lack of privacy and overcrowding of 2 to 3 generations of
the family in the same house is a major problem. Moreover, a HUPA study
of a project in Tirupati, Andhra Pradesh found that while approved
carpet area of each dwelling unit was to be 25.39 sqm, in actual
construction the carpet area was 14.74 sqm and built up area was 20.96
sqm.
Identification and Selection of Beneficiaries
Beneficiary selection and allotment is one of the
most politically coloured processes in these schemes. Politicians use
housing schemes as a means to confer favours upon voters, thus political
tussles often result in unnecessary delays in allotment. The CAG report
by the HUPA highlighted this. A Development Alternatives (DA) study in
Kerala and Madhya Pradesh in 2014 had similar observations. This
political interference also colours repayment rates and schedules among
the allocated units. Consultations with stakeholders in Andhra Pradesh
estimated the non-repayment rate to be as high as 90% in certain
pockets.
Also surveys conducted for identification often have
unclear eligibility guidelines. This process does not take into account
adult children marrying and starting their own families in the duration
of the construction and definitely does not account for future
population growth. The DA study clearly brought this out as a major
source of dissatisfaction among the beneficiaries.
Ownership and
Tenure
Successful community participation and engagement
throughout the process of planning and construction enhances ownership
as the Development Alternatives report highlighted from the Sangli
experience. Moving from a predominantly horizontal ground based housing
plan to an apartment as is the case with most schemes requires some
time. Community based cooperative process can help ease the transition.
Also valuing the asset provided helps build ownership.
While a feeling of ownership can be created among
beneficiaries through various approaches, tenure ship often creates
security concerns. Studies conducted by Development Alternatives showed
that most schemes transfer the house deed to the beneficiary after all
instalments have been paid, with a caveat that prevents them from
selling the asset for a period of 7-15 years. This in practicality is
not enforced, thus people buy and sell (speculation) or sell and return
back to slums (convenience). Also as the land belongs to the government,
sometimes there are not clear documents that highlight the entitlement
of the occupants, keeping alive the fear of eviction.
Supporting
Infrastructure and Living Conditions Not Suitable
Supporting infrastructure plays an important role in
determining retention. HUPA studies show that the reasons vary from
proximity to garbage dumps to narrow approach roads that restrict
movement of people and emergency services like ambulance, police van or
a fire engine. Thus the social infrastructure and land development have
to be undertaken simultaneously with the housing programmes to ensure
that basic provisions and urban facilities are provided to the
occupants.
Thus some of the key aspects that policy makers need
to consider while drafting and implementing housing and habitat policies
are as follows:
Appropriate
beneficiary selection with timely allocation for occupation
Use of resource
efficient materials and technologies to maintain quality
Appropriate size
of houses that meet basic needs and privacy concerns
Social
infrastructure to be developed simultaneously with housing
Appropriate
financial tools and mechanisms in place between all stakeholders
Exploring
alternative innovative models like rental models
q
Kriti Nagrath
knagrath@devalt.org
References
JnNURM &
RAY Progress, September 2013, Ministry of Housing & Urban Poverty
Alleviation
http://pmindia.gov.in/
Sustainable Social Housing Initiative Stakeholder assessment Report ,
DA 2014
Indias Urban
Awakening, Mckinsey Global Institute, 2010
Back to Contents
|