| 
        The Urban Housing Policy 
        Debate
 Housing Programmes Housing for 
        All is a priority commitment for the Indian Government. The vision is 
        that every family will have a pucca (permanent) house with water 
        connection, toilet facilities, 24Χ7 electricity supply and access. The 
        programme proposes to build 20 million affordable houses for the 
        economically weaker section in metros, small towns and all urban areas 
        of India by 2022. The budget has allocated Rs 22,407 crore for the 
        housing and urban development sector for this fiscal year. Housing schemes have been planned and implemented 
        before, without reaching the goal of eliminating homelessness. The 
        Jawaharlal Nehru National Urban Renewal Mission (JNNURM), launched in 
        2005, was the first and biggest effort in the post-independence history 
        of India to comprehensively address urban development. The scheme ran 
        from 2005 to 2014, after being extended by two years for the completion 
        of delayed projects.  In 2012, the Ministry of Housing and Urban Poverty 
        Alleviation (HUPA) pegged the housing shortage at 18.78 million units, 
        with 96% of this demand in the affordable housing space. With the gap 
        expected to grow to 38 million units by 2030 (MGI, 2010), the new target 
        still falls short of eliminating homelessness. Thus it is important to 
        understand the causes behind this implementation gap.  Implementation Gaps While policies do exist, there have been multiple 
        gaps in the 
        translation of these policies into implementation that reduce the 
        impact. A progress study by HUPA in September 2013, showed that only 47% 
        of the dwelling units sanctioned under JNNURM had been completed. In 
        Punjab, 87% of the units sanctioned were either not started (48%) or not 
        completed (39%). The discrepancy between disbursement of Central 
        Assistance (ACA) and completion of dwelling units on the other is 
        particularly striking in some states and highlights implementation 
        difficulties. In Sikkim, 94% of ACA had been released, but only 17.7% 
        sanctioned dwelling units had been built. In Rajasthan, 73.3% ACA had 
        been disbursed, but only 19.3% of units had been completed. A year 
        later, only about 59% of the dwelling units sanctioned across the 
        country had been completed but 87.6% of committed funds were released. 
        Additionally only 43% units were actually occupied.  Thus the scheme was unable to meet its target of 
        providing shelter both due to units not being constructed as well as 
        lack of occupation in the completed units. Low retention and acceptance 
        of social housing projects is not just limited to JNNURM. Similar 
        experiences have been seen in many other state and centrally sponsored 
        housing schemes. A study to gain insights and a deeper understanding of 
        the situation on the ground reflected some causes of these lack lustre 
        statistics. They are illustrated below.   Land 
        Constraints The responsibility for provision of land - a prime 
        resource for housing lies with the government. Consultations with key 
        stakeholders across various states in India revealed that a major 
        bottleneck for affordable housing projects is adequate availability of 
        land. Most medium to large cities do not have enough land near the city 
        centre, thus slums and new housing projects (especially affordable) are 
        relocated on the outskirts of the city, often beyond the municipal 
        boundaries. This relocation adversely affects the displaced populace by 
        removing them from their livelihood, often distancing them from basic 
        amenities like markets, hospitals and schools. Travel routes are also 
        not well developed especially in the smaller towns to ease the 
        transition. This relocation is often quoted as the single most important 
        reason for attrition and desertion of these allotted houses.  Financial 
        Mismanagement The HUPA JNNURM progress study found instances of 
        fund diversion from housing projects towards other initiatives such as 
        toilet construction (Jammu & Kashmir), DPR preparation (Jharkhand), 
        agency charges (Haryana) etc. This has obvious adverse effects on 
        progress.  Another area of concern is the cost escalation due to 
        inflation between the project planning and construction stages. The 
        centres share is fixed. The urban local body or implementation agency 
        often cannot bear this expense and they end up passing it on to the 
        consumer. Further delayed release of funds as is often the case in 
        government projects, exacerbates the situation. Projects often get 
        stalled due to this reason. This was observed in self-financing schemes 
        such as the Rajiv Swah Gruh Scheme in Andhra Pradesh where the 
        implementation agency was unable to bear the costs and the scheme shut 
        down.  Quality of 
        Construction Construction of housing especially in the numbers 
        required to meet the demand is very resource intensive. Resource 
        efficiency in materials and technologies can go a long way in reducing 
        this pressure on resources and the environment as well in reducing the 
        cost of construction. However, they are often not mainstreamed in 
        construction and the government schedule of rates that govern material 
        use. Additionally, limited technical capacities of implementation 
        agencies on these alternative materials and technologies retards the use 
        of these options.  While this is true for all housing and construction, 
        the affordable housing sector faces a serious acceptance issue from 
        users due to the common perception of these alternates. The Kerala 
        experience shows that use of these technologies in institutional and 
        high income construction creates a demonstration effect increasing 
        acceptance within the LIG (Low Income Group) and EWS (Economically 
        Weaker Section) sectors.  Another concern among home owners is the small size 
        of houses allocated. EWS houses are in the range of 21-27 sqm carpet 
        area. This barely accommodates a bedroom, a common room and a tiny 
        kitchen. The lack of privacy and overcrowding of 2 to 3 generations of 
        the family in the same house is a major problem. Moreover, a HUPA study 
        of a project in Tirupati, Andhra Pradesh found that while approved 
        carpet area of each dwelling unit was to be 25.39 sqm, in actual 
        construction the carpet area was 14.74 sqm and built up area was 20.96 
        sqm.   Identification and Selection of Beneficiaries Beneficiary selection and allotment is one of the 
        most politically coloured processes in these schemes. Politicians use 
        housing schemes as a means to confer favours upon voters, thus political 
        tussles often result in unnecessary delays in allotment. The CAG report 
        by the HUPA highlighted this. A Development Alternatives (DA) study in 
        Kerala and Madhya Pradesh in 2014 had similar observations. This 
        political interference also colours repayment rates and schedules among 
        the allocated units. Consultations with stakeholders in Andhra Pradesh 
        estimated the non-repayment rate to be as high as 90% in certain 
        pockets.  Also surveys conducted for identification often have 
        unclear eligibility guidelines. This process does not take into account 
        adult children marrying and starting their own families in the duration 
        of the construction and definitely does not account for future 
        population growth. The DA study clearly brought this out as a major 
        source of dissatisfaction among the beneficiaries.   Ownership and 
        Tenure Successful community participation and engagement 
        throughout the process of planning and construction enhances ownership 
        as the Development Alternatives report highlighted from the Sangli 
        experience. Moving from a predominantly horizontal ground based housing 
        plan to an apartment as is the case with most schemes requires some 
        time. Community based cooperative process can help ease the transition. 
        Also valuing the asset provided helps build ownership. While a feeling of ownership can be created among 
        beneficiaries through various approaches, tenure ship often creates 
        security concerns. Studies conducted by Development Alternatives showed 
        that most schemes transfer the house deed to the beneficiary after all 
        instalments have been paid, with a caveat that prevents them from 
        selling the asset for a period of 7-15 years. This in practicality is 
        not enforced, thus people buy and sell (speculation) or sell and return 
        back to slums (convenience). Also as the land belongs to the government, 
        sometimes there are not clear documents that highlight the entitlement 
        of the occupants, keeping alive the fear of eviction.   Supporting 
        Infrastructure and Living Conditions Not Suitable Supporting infrastructure plays an important role in 
        determining retention. HUPA studies show that the reasons vary from 
        proximity to garbage dumps to narrow approach roads that restrict 
        movement of people and emergency services like ambulance, police van or 
        a fire engine. Thus the social infrastructure and land development have 
        to be undertaken simultaneously with the housing programmes to ensure 
        that basic provisions and urban facilities are provided to the 
        occupants. Thus some of the key aspects that policy makers need 
        to consider while drafting and implementing housing and habitat policies 
        are as follows:  Appropriate 
        beneficiary selection with timely allocation for occupation  Use of resource 
        efficient materials and technologies to maintain quality  Appropriate size 
        of houses that meet basic needs and privacy concerns  Social 
        infrastructure to be developed simultaneously with housing  Appropriate 
        financial tools and mechanisms in place between all stakeholders  Exploring 
        alternative innovative models like rental models 
        
        q Kriti Nagrathknagrath@devalt.org
 References JnNURM & 
        RAY Progress, September 2013, Ministry of Housing & Urban Poverty 
        Alleviation
  
        http://pmindia.gov.in/
  
        Sustainable Social Housing Initiative  Stakeholder assessment Report , 
        DA 2014
  Indias Urban 
        Awakening, Mckinsey Global Institute, 2010
   
        
        Back to Contents |