ANOTHER DAM ON THE SHARAVATHI
- NGOs-MOEF Ensure
Observance Of Guidelines
Gudakesh
Jog Falls : The mist plays hide
and seek with the members of the expert team of the Ministry of Environment &
Forests (MOEF) observing the famed falls which have four distinct ones locally
named Raja, Roarer, Rocket, Rani, each according to its distinct
characteristic. On occasion they can see the Raja without his crown, or the
Rani with her long flowing tresses, then all is lost to the mist; suddenly it
lifts and the four falls can be beheld in their glory. Much of it vanishes
once the flow from the dam (at Linganamakki) upstream of the Sharavathi is
reduced, for then the falls become a trickle. The Linganamakki project was
completed in the sixties for the purpose of providing power to the state’s
industries.
Another dam is under construction downstream of the falls, at the tail end of
the other dams, just before the Sharavathi enters the Arabian sea, hence its
name, the Sharavathi Tailrace Project also known as the Gerusoppa project
(located at Gerusoppa village, Honnavar taluka, Uttara Kannada district,
Karnataka). The MOEF team is here to examine whether the conditions
stipulated by the ministry are being observed so that the forests and its
endemic species are not lost to the Tailrace dam, or the wildlife in the
region harmed.
The Tailrace is the third dam for generating power that the Karnataka Power
Corporation (KPC) is constructing with the concomitant power station. The
other two dams on the Sharavathi are at Linganamakki and Talakalale, The
three power houses are the Linganamakki (two units of 55 MW each), the
Sharavathi station (890 MW, the largest in Asia) and the one near the Tailrace
dam (4 units of 60 MW).
The Sharavathi Tailrace Project was given the green signal (“conditional
environmental clearance”) by the MOEF on March 25, 1987 subject to the KPC
observing eight safeguards noted in its letter. The clearance was revoked on
July 31, 1992 because its stipulations were not being observed by the
corporation. A year and two months later the MOEF re-issued the clearance was
revoked on July 31 1992 because its stipulations were not being observed by
the corporation. A year and two months later the MOEF re-issued the clearance
while imposing 12 safeguards in addition to the eight listed by it on March
25, 1987.
The team visited the dam site at Gerusoppa where it invited local NGOs for
discussion to obtain their perspective on the Tailrace project and the details
on the implementation of the safeguards by the KPC.
Some of the safeguards (guidelines) maybe listed:
1.
The land capability and vulnerability survey in the catchment of the
Sharavathi Tailrace Projects should be carried out to delineate critically
degraded areas needing priority treatment. The amount of Rs. 10 lakhs
presently earmarked for the soil conservation work should be accordingly
enhanced depending on the nature of work and area to be covered.
2.
Even
though no population is going to be effected due to the submergence created by
the project, since sizeable forest area is required to be diverted, measures
should be initiated to ensure nistar rights of local people.
3.
Detailed survey on aquatic flora
and fauna should be carried out to ascertain existence of species like
Mahaseer with plans for their salvation.
4.
Migratory corridors of elephants
should be delineated in consultation with the Chief Wildlife Warden, Karnataka
and vegetation cover in the area should accordingly be enhanced in the
project impact zone.
5.
Since 10 lift
irrigation schemes providing irrigation to about 750 ha are presently under
operation in the downstream stretch of the project, sufficient control
measures should be built into the project operations to ensure that adequate
water is released even in the lean season.
The Tailrace project was contemplated as far
back as the mid-sixties. The dam height will be 58 metres across the
Sharavanthi near Gerusoppa village and the power house will be located “at the
toe of the dam”. The dam will impound water to a full reservoir level
submerging 596 hectares of forest land in the valley. In total 700 hectares
of forests will be lost, a little more than a 100 being taken up by roads,
houses, quarries.
The forests in the Sharavathi catchment area are evergreen or semi-evergreen
type. The Economics Agriculture and Ecology Consortium (EAEC) study points
out that “the project area is covered by southern tropical evergreen forests.
Several biotic factors have considerably reduced the density of these forests
over centuries. The partially closed forests canopy is made up of the
confluent crowns of medium size trees. The dense canopy ensures controlled
conditions of light and degree of humidity within the forest. The banks of
the Sharavathi abounds in plants that are specially tolerant to water-logging
and yield leaves, flower and fruit during the late winter season.” Besides,
treeless, shrubs are found. “The ground cover”, the study adds “has a rich
composition of mesic plants especially during the monsoon months. Mosses are
aplenty, as well as lichens and fungi. The role of fungi in breaking down the
forest debris into simple organic nutrients in the natural process of
recycling is well known.”
A migratory path near Ambepalgudda has been observed; elephants often use it.
The storage of water (in the dam) will restrict their movement within the left
bank which has a vast stretch of forest without human habitation. Wild
animals are scarce on the right bank, perhaps because of human habitation
along the Bangalore-Honnavar road whereas on the left bank the animals are
more secure and live under protective cover of the forest.
Apart from elephants, the other fauna available in the project area include
tiger, panther, langurs, gaur as well as bears and mouse deer. The rare
species found here is the lion-tailed monkey, declared endangered all over the
world. There is a larger population of prey animals than predators.
Among the avian species are the grey jungle fowl, Indian great hornbill,
Malabar pied hornbill, Keel, Hoopi, Brahimini kite.
The studies indicate that there are 34 varieties of fresh water fish,
including the Mahaseet and 27 varieties of entuarine fish species re Tor
Kudree, Tor Musullah, Tor Neilli, Angula species and Labeo callbasu. We are
told that in southern Indian rivers where “abundant economic variety fauna are
found”.
The Tailrace project is under attach for the threat it poses to the above
mentioned flora and fauna --- and more. Almost everywhere dams, in particular
large ones, have been criticised for not being cost-effective, and for the
rehabilitation/ dislocation and environment costs they incur. So far about 58
large, 152 medium, 2155 small reservoirs (total 2365) have been built in
different river basins of India which together have a water spread area of 3
million hectares at the full reservoir level (FRL). India accounts for more
than 50 percent of the total reservoir area in south-east Asia.
Undeniably the most controversial in recent times has been the Narmada
(Gujarat, Madhya Pradesh and Maharashtra) largely because of the failure on
the part of the authorities to re-habilitate the tribals; they have been
shunted off to areas alien to their environment; and even the forest area
where they have been re-settled (as in Maharashtra) has generated controversy
because it has involved the destruction of green cover. In several cases, the
tribals refused to move from their villages, being prepared to drown under the
impounded waters. In the case of Tehri dam (Garhwal) the people have not
shifted even after receiving compensation; Tehri town continues to be occupied
and several residents have even rented their homes. Unlike the Namada oustees,
the residents of Tehri and nearby villages do not fear going under because
once the Soviet Union collapsed, the funds for the project dried up. The
authorities are looking around for resources to continue work on it.
Rehabilitation with regard to the Pooyamkutty dam (Kerala), however, has not
posed a problem because the number of people involved has been limited; in the
case of the Tailrace no rehabilitation is required. The pooyamkutty project
area has among the richest forests and vegetation this write has come across,
as has been documented in these columns earlier. Like Pooyamkutty, the
Tailrace project too is in the Western Ghats and the vegetation is similar,
the potential loss of which has agitated environmental groups in the region.
In fact, they took the matter to the Karnataka high court and at one stage two
cases were pending before it. The MOFF clearance was revoked as a result of
the high court order of January 1991 with reference to the court petition No
8170 filed in 1988 by the Sharavathi Tailrace Yojana Horata Samiti and the
Honnavar Taluka Parisara Koota.
The NGOs cite the report of the deputy conservator of forests, Hunnavar (Prabhu)
who opposed submersion in 1985 observing that the forest’s “micro environment
will be damaged”. Others too have opposed the project. The report of Dr.
Subhaschandran of the loss of the “richness and biodiversity of the valley”.
The 1990 report of Dr. K.M. Safeeulla, the then vice chancellor of Mangalore
university, demanded that the project be halted to save the Sharavathi valley.
The studies have identified several new species of plants and fungi that would
be endangered by the project. One study noted that among the six endangered
species of Mahaseer, four were to be found in the Tailrace project area. The
project would pose a threat to other rare species like the King Cobra, lion-
tailed macaques (for whose preservation the Silent Valley Project was halted)
and the migratory path of elephants would be disturbed.
The NGOs, who base their criticism on the above reports as well as they study
of the Central Water Commission in 1973 and the project report of 1981, point
to the technical defects of the dam. The geological one is that the KPC,
which initially began in the construction of the powerhouse on the left bank
of Sharavathi, shifted it to the right bank, because of the geological faults,
“but now the powerhouse will be occupying the same site as the embankment line
on the right bank which was shifted 150 metres upstream’.
Initial studies indicated heavy seepage along the periphery. Though KPC has
taken into account the loss as a result of evaporation, it has not done so
with regard to seepage. Moreover, the water inflow for the Tailrace project
is calculated upto 1980. But since it has reduced each successive year, this
is a major lapse on the part of KPC.
Apart from the environmental and technical objections, the NGOs led by Ganesh
Bhat of the Sharavathi Tailrace Yojana Horata Samiti and Anant Hegde of Save
Western Ghats Movement, have several on socio-economic grounds as well. They
observe that the downstream effects of the project have not been given
sufficient attention: (I) the Sharavathi river joins the Arabian Sea no more
than 32 km from the dam site. The salt-water effect is upto five kilometres
from the sea; if this “band” shifts further upstream and the river water turns
brackish, thousands of farmers who use the river, will suffer; (ii) the nistar
rights of the people of the region has/will be affected as also (iii) the
fuelwood supply of the local population.
Then there is the manner in which the project is being implemented. At the
quarry in the forest some distance from the dam site from where material
(rock, stone, rubble) for the dam construction is collected, the blasting
operations are producing vibrations, gases, dust and sound which are affecting
the fauna of the region, so much so that Dr. Kusuma, President of Honnavar
Taluka Parisar Koota said she had to treat victims of animal attacks living
around the dam site.
The labour force of 500 people is expected to be supplied fuelwood by the
contractor (Mr. Sundar) from outside the forest area. But there is no way of
checking that the labour does not on the quiet secure some of its fuelwood
requirements from the forests, as also indulge in poaching.
The compensatory afforestation/catchment area treatment by the KPC has to be
done as per the (I) Forest Conservation Act and (ii) the Environment
Protection Act. In accordance with the Forest Act, the survival rate of
saplings on parts of the 680 hectares that have been examined by the forest
department, is as high as 90 percent. However, the KPC has so far not even
submitted its plans to undertake catchment area treatment of 700 hectares as
per the Environment Act.
The KPC’s response to some of the major allegations is as follows:
The plants termed as endemic to the Tailrace project area are not endemic to
it. They have wide distribution throughout the Western Ghats. Regarding
nistar rights, it has been observed that locals collect green and dried
leaves for manure, as well as bamboo and reeds. But they have no other
rights over the forest as it is a reserved forest.
The upstream of the Sharavathi river (below jog falls) is a deep cut valley
with fairly steep slope in a mountainous terrain and as such the chances of
seepage are very remote in the vicinity. The water loss tests conducted “in
the overburden at FRL (full reservoir level) indicate that the seepage losses
are negligible.”
The downstream of the proposed dam site is a coastal plain with small
agricultural fields growing paddy; areca and coconut are cultivated by lift
irrigation. The utilisation of water for lift irrigation is very meagre
compared to the quantity of water flowing in the river during different months
of the year.
Before the construction of the dams on Sharavathi, the river used to be active
during the monsoon and almost dry during summer. The tidal water would extend
up to Gerusoppa village making the water saline after the monsoon. After
impoundment at Linganamakki and Talakalale and the consequent constant flow in
the river, the impact of tidal water has been pushed beyond Hosadi village.
On completion of the Tailrace project, the flow will not decrease, rather it
will increase and hence there is no possibility of inpushing of saline water.
As long as the thrust and parry process between the NGOs and the KPC continue,
there is a good chance of the MOEF guidelines being implemented. But their
implementation is dependent on the multi-disciplinary high-power committee
that has been set up (as per the guidelines). However, it has met only
once. In the circumstance, the project implementor (the KPC) is burdened with
the responsibility of also enforcing the guidelines, a rather unrealistic
situation in terms of (a) impartiality and (b) availability of expertise.
Both these are essential for the protection/preservation of the Sharavathi
Valley’s flora and fauna, a job that only the high power committee can do.
Why is the Karnataka government preventing it from doing its job?
Extract from Monoo Nalapat’s interview
with Maneka Gandhi, the then minister of state for environment and
forests, published in The Times of India of August 14, 1990. Ms. Gandhi
stated :
“Or take a second example of a scam in the name of ‘development’ the
so-called ‘Tail Race dam’ in Sharavathi in Karnataka. We were told that
yes, thousands of acres would be submerged but that this was all
‘barren’ land. A bureaucrat from the Centre went down to Karnataka and
reported, after checking the site, that the land was indeed ‘totally
barren’.
‘Then I started getting complaints of animals attacking humans, animals
that had been driven to human habitats by the cutting down of their
forests. How could there beforests in a ‘barren’ area? I sent an
officer - an honest one this time - to investigate, and he told me that
the land (to be submerged) was in fact a thick rain forest. Each tree
that is cut would be worth several thousand rupees, and they would all
be stolen be the contractor, as the land is on paper supposed to be
‘barren’.
“The proposed dam would destroy two to three thousand hectares of
forest, and in return electrify and irrigate only a few villages. But
officials, contractors and their political henchmen would rake in crores,
which is why the project is being demanded.” |
Back to Contents
|